Timeline as of November 4, 2024
The current timeline determined by CORE can be found here
10/10 – 10/18 - UAT (Bothell) completed
10/21 – 10/22 - CORE compilation and review of all reported issues
10/23 – 11/1 - Correction of UAT issues (CORE)
11/4 – 11/8 - 2nd UAT (Bothell) -- Delayed (11/4)
11/12 – 11/15 - Final issue resolution (CORE)
We’ll evaluate these new dates as we move through the rest of the process. The next steps look as follows:
-
Bothell will complete the first round of UAT on 10/18.
-
CORE will compile all issues and determine fixes on 10/21 and 10/22.
-
CORE will provide a timeframe for issue resolution following our work on 10/22.
-
CORE will work on making any changes requested in the first round of UAT beginning on 10/23.
-
CORE will then release the site back to Bothell for another week of testing.
-
CORE will resolve any of the issues found in the second round of testing and then the site will be ready to move to the production environment.