Bothell IT Projects
More
Active projects
|
|
|||||||
|---|---|---|---|---|---|---|---|
|
|
2025 WORKPLAN | On track | checked | Feb 25, 2025 |
|
||
|
|
APPS - Customer Payment Portal - (fm 2024) | Off track |
Preview not available
|
checked | Jul 24, 2023 |
|
|
|
|
GIS - Comp Plan Support (GIS) - Fm 2024 | On track |
Apr 25 - Final maps received from consultant, reviewed and returned
|
checked | Jan 28, 2025 |
|
|
|
|
GIS - Council Priorities Data Map | On track |
05/2025 - Draft is in progress with goal to fully build out the Environmental Stewardship page 1st and present to ELT on 5/22
|
checked | Aug 08, 2024 |
|
|
|
|
OPS - 2024 City Hall to Fire 42 Fiber - From workplan #522 | On track |
5/13/2025 - No change in status.
|
checked | Jan 02, 2025 |
|
|
|
|
OPS - Facilities Camera Replacement | On track |
4/1/2025 - Switch & cable work is installed & completed and awaiting further opportunities.
|
checked | Feb 26, 2025 |
|
|
|
|
OPS - Network Redundancy | On track |
4/1/2025 - Working on the network mapping. ETA: 3rd quarter 2025.
|
checked | Feb 26, 2025 |
|
|
|
|
Fleet Replacement | On track |
5/7/2025 - Fleetio is starting the hand off process. Going from the implementation pm to account management.
We increased the vehicle count from 250- 300 in the system. Getting the newest data in RTA to Fleetio to import into the system. Compiling vendor information to Fleetio to import into the system. |
checked | Oct 09, 2024 |
|
|
|
|
Volunteer Software for Parks | On track |
5/7/2025 - One more training and the application is live. Staff has determined there are tools within the program that they were unaware of but are learning will enhance productivity. Go live late May
|
checked | Apr 03, 2024 |
|
|
|
|
Wireless Upgrade/replacement | On track |
4/1/2025 - 29 of 37 WAPs completed. Approximately 8 remaining.
|
checked | Aug 09, 2024 |
|