OPS - Facilities Camera Replacement | checked |
4/1/2025 - Switch & cable work is installed & completed and awaiting further opportunities.
|
|
|
|
OPS - Network Redundancy | checked |
4/1/2025 - Working on the network mapping. ETA: 3rd quarter 2025.
|
|
|
|
2025 WORKPLAN | checked |
|
||
|
GIS - Comp Plan Support (GIS) - Fm 2024 | checked |
Apr 25 - Final maps received from consultant, reviewed and returned
|
|
|
|
OPS - 2024 City Hall to Fire 42 Fiber - From workplan #522 | checked |
5/13/2025 - No change in status.
|
|
|
|
Fleet Replacement | checked |
5/7/2025 - Fleetio is starting the hand off process. Going from the implementation pm to account management.
We increased the vehicle count from 250- 300 in the system. Getting the newest data in RTA to Fleetio to import into the system. Compiling vendor information to Fleetio to import into the system. |
|
|
|
Wireless Upgrade/replacement | checked |
4/1/2025 - 29 of 37 WAPs completed. Approximately 8 remaining.
|
|
|
|
GIS - Council Priorities Data Map | checked |
05/2025 - Draft is in progress with goal to fully build out the Environmental Stewardship page 1st and present to ELT on 5/22
|
|
|
|
Volunteer Software for Parks | checked |
5/7/2025 - One more training and the application is live. Staff has determined there are tools within the program that they were unaware of but are learning will enhance productivity. Go live late May
|
|
|
|
APPS - Customer Payment Portal - (fm 2024) | checked |
5/29/2025 - A contract addendum is in process
|
|