checked | 2025 WORKPLAN | On track |
|
||
4/1/2025 - Switch & cable work is installed & completed and awaiting further opportunities.
|
checked | OPS - Facilities Camera Replacement | On track |
|
|
4/1/2025 - Working on the network mapping. ETA: 3rd quarter 2025.
|
checked | OPS - Network Redundancy | On track |
|
|
checked | Phone Modernization (cont. fm 2024) | On track |
|
||
3/4/2025 - Light and connectivity testing completed. Next steps: Map out connections, ETA completion appx. May 2025
|
checked | City Hall to Fire 42 Fiber - From workplan #522 | On track |
|
|
Apr 25 - beta application being shared withing PD (not GIS) Mar 25 Esri Demo and HUB selected by PD. Chad has interest, time and talent for technical lead deployment. ETS in minor backup role to potentially assist. Jan 24 Council, CM, Polic chief desire to replace crimemapping.com Aug 24, status unclear.
|
checked | Comp Plan Support (GIS) | On track |
|
|
4/10/2025 - Status still waiting for Metrics from Exec.
Site: https://bothell-2040-vision-bothellgov.hub.arcgis.com |
checked | Council Priorities Data Map | On track |
|
|
4/22/2025 - CORE BT has been notified that the team does not have confidence in the product and wish to discontinue meetings and terminate the relationship. Other option is Tyler Resident Access - the integration into Munis is a key reason. No scripting by staff, no import and export by staff thereby reducing staff involvement/requirements for SQL knowledge. Resident access is also set up exactly the way Utilities staff requires for billing.
|
checked | Customer Payment Portal | Off track |
|
|
4/2/2025 - Team is configuring the interface. Continue to alter & schedule the PM-A Service Program to specifications, and finish buildout of the PM-A inspection form. Once built, the two will be used together to create issues for items needing attention, to be resolved during the PM-A Work Order.
|
checked | Fleet Replacement | On track |
|
|
4/10/2025 - Staff is still in training and linking will be on Bothell's website late May.
Site: bothellwa.cervis.com |
checked | Volunteer Software for Parks | On track |
|
|
4/1/2025 - 29 of 37 WAPs completed. Approximately 8 remaining.
|
checked | Wireless Upgrade/replacement | On track |
|