Project extended per PW
Email changes & testing issues
Project completed, Annual Report submitted to Department of Health
As of May 1st, we are now on Maintenance mode on the project.
Project extended to May
A change order has been submitted to move the end of project to May.
New Feature in VEPO
Now testers can upload the PDF version of their license!
Progress on Annual Report - Testers still adapting
Key staff out on Paternity leave and team fills the gap. Testers reporting angst over registering.
Project extended to March!
Confirming the annual report, tester confidence and staff editing mistakes.
VEPO Backflow is online!
The City of Bothell is no longer accepting any tests in the form of email or snail mail!!
Backflow application goes live Monday, December 4th!!
Tester trainings went very well with over 60 testers in attendance!
Tester Training all set for week of 11/27
The VEPO system is ready for Tester training!
Admin Training Completed
Training completed for PW / IT staff
ADMIN Training date set
11/16/2023
Test forms under review
Reviews include test forms, customer letters and automated notifications.
Tester notifications sent, Tester training dates set
Letters sent to Testers in regard to the new system and training dates
Workshop dates for the rest of October
Workshops for testing and verification of tests will be on the next TWO Mondays
Key DATES Determined
These are the dates for training - both admin staff & Testers - and for GO LIVE!!
VEPO has our data
Kudos to Jennifer Fry for getting our Backflow data to the VEPO team in record time!
VEPO kickoff confirmed!
Contract has been approved by VEPO and BOTHELL and 9/5 kickoff is a GO!
Tentative Kick Off dates set!
Three dates are scheduled as placeholders but only one will be selected.
Contract going to vendor
PW completed the contract as payment for the application will be out of PW Budget
VEPO Contract in Process!
Working with Catherine, Legal Consultant and Vendor to get contract out.